Các nhà máy điện gió đóng góp lớn vào sản lượng điện trên địa bàn tỉnh Gia Lai

The Gia Lai Provincial People’s Committee has just approved the investment policy and at the same time approved the investors for 7 wind power projects with total capital of VND 11,776 billion. The projects are concentrated in the areas of Ia Le, Chu Puh, Phu Thien and Bau Can (Chu Prong).

Scale of each project

  • TNE 1 Wind Power: 45 MW, capital of VND 1,840 billion, in Ia Le, Chu Puh, Phu Thien.
  • TNE 2 Wind Power: 45 MW, capital of VND 1,828 billion, in Ia Le, Phu Thien.
  • TNE 3 Wind Power: 45 MW, with an investment of VND 1,830 billion, in Ia Le, Phu Thien.
  • Chu Puh Wind Power 1.1: 45 MW, investment capital of VND 1,852 billion, in Chu Puh, Ia Le.
  • Chu Puh Wind Power 1.2: 45 MW, investment capital of VND 1,811 billion, in Chu Puh.
  • Thang Hung Wind Power: 42 MW, investment capital of VND 1,385 billion, in Bau Can, Chu Prong.
  • Thang Hung Wind Power Phase 2: 38 MW, with investment capital of VND 1.23 trillion, in Bau Can.

Progress and significance

Five projects in Ia Le, Chu Puh and Phu Thien are expected to break ground in February 2027 and be completed and put into operation in December 2028. The two Thang Hung projects are expected to break ground in December 2026 and be completed in March 2028. The projects have an operating term of 50 years.

Once operational, the plants will add clean power to the national grid and harness the local renewable energy potential. For businesses operating in infrastructure construction and heavy equipment, the approval of a series of projects creates demand for site levelling, access roads, turbine foundation pedestals, and the mobilisation of construction equipment in the 2027–2028 period.

Partners and customers interested in partnership programs with Quang Duc, please contact the hotline 0962 991 179 or email info@qdgl.com.vn.

Source: Gia Lai Newspaper (23 June 2026). Photo: Vu Thao, Gia Lai Newspaper.